Job costing for electricians, plumbers and builders

How to cost a job so labour, materials and extras show a real profit, for Australian electricians, plumbers and builders. Not financial advice.

General information only, not tax, legal or financial advice.

A charge-out rate is the picture for the year. A job is one switchboard, one bathroom, one extension. You can have a sound rate and still lose Tuesday, because the materials were wasted, the hours blew out, or a “small” extra was never priced. Job costing is how you see that before the quote goes.

This is the method behind the Charge-Out Rate & Job Costing Calculator. That file is not finished and not for sale. The arithmetic below is so you can do it on a pad, and so the sheet makes sense when it exists. It is not a quote for your next job.

Electricians, plumbers and builders do not need three versions of this. The labels change. The structure does not: labour you sell, materials you sell, extras you sell, set against what they cost you, with GST in its own column.

A good year can still hide a bad job

You can still price “one like that” from memory. The last one had materials on site, a client who decided, and no return visit. This one has none of those. The invoice matches. The profit does not.

Put the lines in the open. Hours, by person if more than one of you is on it. Materials at what you pay, then wastage, then the markup you mean. Extras named. At the bottom, profit in dollars and margin as a percentage of the sell price excluding GST. A healthy materials markup can hide labour you sold too cheap if you only look at the total.

Labour: the price and the cost are different numbers

Sell the hours at the charge-out rate you chose. Cost the hours at the true hourly cost, the breakeven, not at the charge-out rate and not at the wage.

That split is the whole point. The charge-out rate includes margin. If you also treat it as your cost, every job looks profitable, including the ones that are not. If you cost labour at the wage alone, you ignore the ute, the insurance and the hours you never billed, and every job looks better than the year will.

Say the true hourly cost is A$97.63 and the charge-out rate is A$122.04. Those two numbers are from a fictional example further down. They are not a going rate. Eight hours sold is 8 × 122.04. Eight hours cost is 8 × 97.63. The gap is the labour profit on that job, before you look at materials. If you sell the labour below 97.63, the job starts in a hole. Materials might fill the hole. They might also disguise it. Show the labour profit on its own so you can see which one happened.

How to build the 97.63 and the 122.04 is the other article: how to calculate your charge-out rate in Australia. The free calculator will get you the rate. It will not cost the job. That limit is deliberate. A job sheet with materials and wastage is the workbook, not the lead magnet.

Materials, wastage and markup

Start with the cost excluding GST. If you are registered, you generally claim the GST on business purchases back, so the GST on the supplier’s invoice is not the cost of the fitting. The rate is 10%, and registration is generally required at a GST turnover of $75,000. Both are on the ATO page how GST works. This article is not telling you whether you must register.

Then wastage: offcuts, breakages, the extra metre. Five percent of A$450 is A$22.50. Forgetting it is how a neat quote becomes a messy job. Materials markup is not the labour margin. Keep them as separate decisions.

The sell price of the materials is: cost × (1 + wastage) × (1 + markup). Using the figures above, A$450 × 1.05 = A$472.50, and A$472.50 × 1.20 = A$567.00. The profit on the materials is the sell price minus the cost including wastage, not minus the original A$450 only. You do not get to count the wasted stock as profit.

Do not price fuel twice

If the vehicle’s fuel, finance and repairs already sit inside the hourly rate, they are recovered every billed hour. Putting that fuel in again as a job cost counts it twice. You can still charge a travel fee. The fee is income. If there is no extra cost, the cost of that line is zero. Write that down.

A hire, a permit, a tip fee, a subcontractor, or after-hours that is not in the normal rate goes on its own line, with a cost and a sell price. A lump called “misc” is how those lines disappear.

Profit and margin, on the job

Add labour, materials and extras. That total, excluding GST, is the job price before tax. GST, if you are registered, is added on top. Profit stays on the ex-GST total. GST you remit is not profit.

Profit is the ex-GST sell price minus hours at the true hourly cost, materials including wastage, and the cost of extras. Margin is that profit divided by the ex-GST sell price. A job with no sell price has no margin.

Margin and markup will not match. Materials markup can lift the job margin above the labour margin. Discounted labour can pull it under. If the only healthy number is the materials line, you are a merchant who happens to carry tools. Know that on purpose.

A fictional job, end to end

Same warning as the rate example. This job is fictional. “Smith kitchen lighting upgrade” is not a client. The rate comes from the fictional one-person year in the charge-out article: true hourly cost A$97.63, charge-out A$122.04, business registered for GST at 10%. None of those are recommended prices.

The job: 8 labour hours, materials cost A$450 ex GST, 5% wastage, 20% materials markup, an A$80 travel fee. The fuel is already inside the vehicle costs that built the hourly rate, so the cost of the travel fee is zero.

Line Amount
Materials including wastage A$450 × 1.05 = A$472.50
Materials sell price A$472.50 × 1.20 = A$567.00
Labour sell price 8 × A$122.04 = A$976.32
Travel fee A$80.00
Job total, ex GST A$1,623.32
GST at 10% A$162.33
Total including GST A$1,785.65
Labour cost 8 × A$97.63 = A$781.04
Job cost A$781.04 + A$472.50 + A$0 = A$1,253.54
Profit A$1,623.32 − A$1,253.54 = A$369.78
Job margin A$369.78 ÷ A$1,623.32 = 22.8%

The margin sits a little above the 20% labour margin because of the materials markup. That is what you want to be able to see. If the labour had been sold at A$90, under the A$97.63 cost, the materials could still have made the total look acceptable. A sheet that only shows one profit number would have let that through. A sheet that shows labour profit on its own would not.

If you want to check the rate half of this example, load the fictional year in the calculator. It will not reproduce the job lines. Those stay on paper until the workbook is finished.

What to look at before you send the price

Five answers are enough before you send the price.

  1. Are the hours realistic, including a return visit if this sort of job usually has one?
  2. Is labour sold at or above the true hourly cost, not just above the wage?
  3. Did wastage get a number?
  4. Are extras listed, and is fuel counted once?
  5. What is the margin on the ex-GST total, and will you do the job at it?

If the last answer is no, change the price or the scope before you send it. Discounting after you have seen the margin is a decision. Discounting because you never costed it is a leak.

A job costing spreadsheet for trades is only useful if you will fill it in when you are tired: obvious input cells, a short list of lines, a total you can read. The printout is for you. What the client sees is a separate piece of paper.

When the workbook is ready it will hold a modest list of jobs, not a set of accounts. It will not replace your bookkeeper. Until then the discipline is the same on paper: sell price, cost, profit, margin, and a note about what you refused to count twice.

If the numbers on a real job surprise you, that is the system working. If you are unsure what to do with them, talk to your accountant before you rebuild your whole price list off one bad week. General information only, not tax, legal or financial advice.

General information only, not tax, legal or financial advice.